Friday, June 25, 2010
Week 11: Day 5
The new hood duct cover arrived and was installed as well as the new frig. The matching frig front will be installed Monday. The painter was out finishing up the details inside and outside. New pics will be posted once the final clean is complete next week.
Monday, June 21, 2010
Week 11: Day 1
There was a lot of work completed last week. Electrical finish was set. Finish plumbing was installed. The new furnace was installed so no more cold winters. The appliances were set and the finished cabinetry panels were set. The oven has yet to ship and the hood needs a new duct cover so there are a few more things to be completed.
We had a final inspection today and it went very well. Everything looked good but the hood needs to be complete and a new earthquake valve for gas needs to be installed. With the replacement part for the hood due in Thursday we will have to wait until Monday for the reinspection.
Tuesday, June 15, 2010
Week 10: Day 2
Monday, June 14, 2010
Week 10: Day 5
Thursday, June 10, 2010
Week 10: Day 4
Week 10: Day 3
Tuesday, June 8, 2010
Week 10: Day 2
Monday, June 7, 2010
Week 10: Day 1
Sunday, June 6, 2010
Week 9: Day 6 & 7
Friday, June 4, 2010
Week 9: Days 2-5
I got a little behind on the posting but that doesn't mean nothing happened. The electrician transfered power to the new meter/panel and removed the old service and feeder cleaning up the side a little. The carpenter installed the wainscoting at the desk and reinstalled door casing and trim at the basement and powder room doors. But the two biggest changes are the new ceaser stone counters and final sanding, prep and staining of the original wood floors.