Wednesday, July 7, 2010

Week 13: Day 1









































































The oven and warming drawer arrived Tuesday and was installed. Her are the most recent pictures

Friday, July 2, 2010

Week 12: Day 4

































































The building inspector was out Thursday and signed off the project. We did the final clean inside and out. Everything was dusted and wiped down, the walls, drawers and cabinet boxes. The frig and matching panels are in and the new hood duct cover is complete. We still have the oven to be installed as it just arrived and will be going in on Tuesday.

Friday, June 25, 2010

Week 11: Day 5

The new hood duct cover arrived and was installed as well as the new frig. The matching frig front will be installed Monday. The painter was out finishing up the details inside and outside. New pics will be posted once the final clean is complete next week.

Monday, June 21, 2010

Week 11: Day 1



















































There was a lot of work completed last week. Electrical finish was set. Finish plumbing was installed. The new furnace was installed so no more cold winters. The appliances were set and the finished cabinetry panels were set. The oven has yet to ship and the hood needs a new duct cover so there are a few more things to be completed.

We had a final inspection today and it went very well. Everything looked good but the hood needs to be complete and a new earthquake valve for gas needs to be installed. With the replacement part for the hood due in Thursday we will have to wait until Monday for the reinspection.

Tuesday, June 15, 2010

Week 10: Day 2

































The island counter top is installed with the induction cooktop in and the sink set. All the finished cabinetry panels are installed except the matching appliance fronts. The electrician has power ready for the appliance install Wednesday.

Monday, June 14, 2010

Week 10: Day 5















The finished cabinetry panels and drawer faces were installed Friday. The island countertop was also brought out and installed. It is solid walnut butcher block.

Thursday, June 10, 2010

Week 10: Day 4

































I was hoping to have pictures of the newly stained and sealed wainscot and trim but everything was covered up with plastic. The ceiling and walls were being touched up for the final coat of paint.