The oven and warming drawer arrived Tuesday and was installed. Her are the most recent pictures
Wednesday, July 7, 2010
Friday, July 2, 2010
Week 12: Day 4
The building inspector was out Thursday and signed off the project. We did the final clean inside and out. Everything was dusted and wiped down, the walls, drawers and cabinet boxes. The frig and matching panels are in and the new hood duct cover is complete. We still have the oven to be installed as it just arrived and will be going in on Tuesday.
Friday, June 25, 2010
Week 11: Day 5
The new hood duct cover arrived and was installed as well as the new frig. The matching frig front will be installed Monday. The painter was out finishing up the details inside and outside. New pics will be posted once the final clean is complete next week.
Monday, June 21, 2010
Week 11: Day 1
There was a lot of work completed last week. Electrical finish was set. Finish plumbing was installed. The new furnace was installed so no more cold winters. The appliances were set and the finished cabinetry panels were set. The oven has yet to ship and the hood needs a new duct cover so there are a few more things to be completed.
We had a final inspection today and it went very well. Everything looked good but the hood needs to be complete and a new earthquake valve for gas needs to be installed. With the replacement part for the hood due in Thursday we will have to wait until Monday for the reinspection.
Tuesday, June 15, 2010
Week 10: Day 2
Monday, June 14, 2010
Week 10: Day 5
Thursday, June 10, 2010
Week 10: Day 4
Week 10: Day 3
Tuesday, June 8, 2010
Week 10: Day 2
Monday, June 7, 2010
Week 10: Day 1
Sunday, June 6, 2010
Week 9: Day 6 & 7
Friday, June 4, 2010
Week 9: Days 2-5
I got a little behind on the posting but that doesn't mean nothing happened. The electrician transfered power to the new meter/panel and removed the old service and feeder cleaning up the side a little. The carpenter installed the wainscoting at the desk and reinstalled door casing and trim at the basement and powder room doors. But the two biggest changes are the new ceaser stone counters and final sanding, prep and staining of the original wood floors.
Friday, May 28, 2010
Week 8: Day 5
All of the crown and trim is in. The pantry pocket door is in and trimmed out. The kitchen sink and counter subtops are in and ready for countertops. The cabinetry finishers are out today for touchup. The cabinet drawers and doors will be installed after flooring is finished. More pictures will be posted shortly.
Wednesday, May 26, 2010
Week 8: Day 3
Tuesday, May 25, 2010
Week 8: Day 2
The kitchen sink counter and island cabinets are installed and refrigerator end panels are being installed.
The base cabinets for the desk are installed and the template for the the slab counter top is being fabricated. The kitchen sink was set in place the counter top template was also completed. Fabrication should take about a week and will be installed next week along with the backsplash.
Monday, May 24, 2010
Week 8: Day 1
The cabinetry arrived today after an extended drying time. Most of the pieces are stacked outside waiting to go in after the toe-kicks are leveled and secured.
The kitchen sink elevation is almost in and then they will move on to the Island and desk cabinetry.
On Friday the new back door was installed.
Thursday, May 20, 2010
Week 7: Day 4
With the damp weather the finishers needed extra time to allow the paint to dry and were done on Wednesday. The cabinetry finishing also need an extra day and will be out Friday instead of today.
Monday, May 17, 2010
Week 7: Day 1
Friday, May 14, 2010
Week 6: Day 5
Wednesday, May 12, 2010
Week 6: Day 3
Monday, May 10, 2010
Week 6: Day 1
Friday, May 7, 2010
Week 5: Day 5
Wednesday, May 5, 2010
Week 5: Day 3
The new electrical meter panel and conduit was completed and is ready for LADWP Inspection. A few of the appliances were delivered so the cabinet contractor could make custom wood panels for the hood and wine cooler.
Week 5: Day 2
I was not able to be onsite today as I was taking the new EPA Lead safety for Renovation, Repair & Painting course, but will be onsite Wednesday.
Monday, May 3, 2010
Week 5: Day 1
Friday, April 30, 2010
Week 4: Day 5
Today is another quiet day. Drywall mud is drying, Cabinetry is being fabricated and finished in the shop and the new back door, plumbing fixtures and appliances are on order.
Week 4: Day 4
With the first part of cabinetry in, we could now start finishing the drywall. The first coats of drywall mud went on today and will need a few days to dry.
Week 4: Day 3